Project Planning Schedule
Below is an outline of the current project planning schedule. Continue to check back for updates as planning moves forward.
May 14 – End of June, 2012
Remarketing and repurposing of remaining machinery, equipment and other assets through online auctions utilizing Orbitbid.com.COMPLETED
Fall 2012
Demolition and abatement cost research scheduled updated and presented to City officials.COMPLETED
Mid to late April 2013
Completion of the highest and best use study to create a potential vision for future development of the former Mt. Pleasant Regional Center property.Spring/Summer 2013
Tentative timeframe for demolition of existing facilities on property.